Releasing retention for subcontracts
To release retention for a subcontract:
- Open 6-7-1 Subcontracts.
- Select the subcontract.
-
In the Retention box, do one of the following:
- Enter the new rate of retention.
- Leave the box blank for zero retention.
- On the Options menu, click Recalculate Retention.
- In the New Due Date for Invoices box, enter the due date you want to assign the invoices.
-
Under Recalculation Option, do one of the following:
- Select to update Only invoices with Retention, or
- Select to update All invoices.
- Click OK.
- Click > .